Fire Rescue and police are on the scene of a gas leak at the Boca Bridges construction site on the border of Boca and Delray on Lyons Road. (Photo: BocaNewsNow.com)
UPDATE: 11:34 — From police/fire rescue — the road has reopened.
UPDATE: 11:11a The leak is capped but the closures continue.
BOCA RATON, FL (BocaNewsNow.com) — (8:45a) — Lyons Road is closed between Clint Moore and Seven Bridges/The Bridges as rescuers work to cap a gas leak in the Boca Bridges construction site. The leak is on the east side of the road.
Fire Rescue’s special operations team is on the scene. We’re told the closure could continue for several hours. BocaNewsNow.com has learned that construction equipment punctured a gas line. The construction site is overseen by GL Homes.
The construction site has been largely evacuated. Traffic, already bad on Lyons due to the construction sites on the east and west sides of the road, is at a standstill as of 9:01 am. Southbound traffic is attempting to turn around in a narrow section of the road. Our guidance: turn around in the area of The Bridges and Seven Bridges which is just before the scene.

Traffic is at a virtual standstill southbound on Lyons Road just before the scene. (Photo: BocaNewsNow.com)
…developing…