BOCA RATON, FL (BocaNewsNow.com) (Copyright © 2026 MetroDesk Media, LLC) — There are 215 projects underway this week on state and local roads that are more likely than not going to mess with you.
The headliners this week: overnight full ramp closures on Florida’s Turnpike at Okeechobee Boulevard, final paving on South County Road in Palm Beach, a brand-new $54 million I-95 project at Northlake Boulevard, and a parade of FPL crews camped on Military Trail, Seacrest Boulevard and Haverhill Road. FDOT’s report covers Nov. 13–20; the county’s covers Nov. 16–22. Here’s all of it, sorted so you can find your own personal misery.
Major FDOT Highway Projects
Interstate 95
The I-95 at Boynton Beach Boulevard Interchange Improvements Project ($64 million, finish date early 2029) keeps grinding along with bridge widening, ramp widening and new turn lanes.
- One I-95 lane may close in each direction starting at 8 p.m., with up to three lanes closed 10 p.m.–6 a.m., Sunday night through Friday. A fourth lane may close overnight as needed.
- Northbound and southbound outside deceleration lanes and shoulders approaching the Boynton Beach Boulevard exits are closed through late 2026.
- Additional ramp lanes may close nightly, 9 p.m.–6 a.m., Sunday night through Friday.
- Eastbound Boynton Beach Boulevard is down to two through lanes from NW 8th Street to east of W. Industrial Avenue through late 2026; the northbound outside turn lane on NW 8th Street at Boynton Beach Boulevard is also closed.
- Boynton Beach Boulevard from Old Boynton Road to NW 3rd Avenue may lose one lane each direction, 9 p.m.–6 a.m., nightly.
- The westbound Boynton Beach Boulevard turn lane to the southbound I-95 on-ramp may close 9 p.m.–6 a.m., Sunday night through Friday. Detour: U-turn via W. Industrial Avenue.
- The driveway and front lot at 650 Boynton Beach Boulevard is closed around the clock through late 2026; use NW 8th or NW 7th Street to NW 1st Avenue to reach the back lot.
- U.S. 1/North Dixie Highway and I-95 Lighting Project (Lake Worth Beach) — $2.5 million. One lane of North Dixie Highway closes intermittently between 24th Avenue South and South Lucerne Avenue, 8 p.m.–4 a.m., Monday, Nov. 16 through Thursday, Nov. 19.
- I-95 at Northlake Boulevard Interchange Improvements Project (Palm Beach Gardens) — $54 million, started Friday, Nov. 13, finish date late 2029. Repaving, wider exit ramps, a fourth through lane on Northlake under I-95, and new turn and bike lanes. All lanes are open for now. Enjoy it.
Southern Palm Beach County (Boca Raton, Highland Beach, Delray Beach)
- U.S. 1 Resurfacing Project (Boca Raton) — $6.3 million, Camino Real to NE 8th Street/Mizner Boulevard. Traffic between Camino Real and SE 5th Street/SE Mizner Boulevard is now in its final pattern in the two left lanes. Southbound loses a lane intermittently 8 a.m.–3 p.m., Nov. 16–20. One lane each direction at Camino Real closes intermittently 8:30 a.m.–4 p.m., Nov. 16–20, for signal work. Between SE 5th Street/SE Mizner Boulevard and NE 8th Street/Mizner Boulevard, U.S. 1 drops to one lane, 9 a.m.–4 p.m., weekdays through late 2026.
- U.S. 1 Bus Shelters Project (Palmetto Park Road to Northlake Boulevard) — $2.3 million. One northbound and one southbound lane close intermittently at NE 20th Street and at Spanish River Boulevard in Boca Raton, 10 a.m.–2 p.m. and 8 p.m.–7:30 a.m., Nov. 16–20.
Central Palm Beach County (Boynton Beach, Lake Worth Beach, Royal Palm Beach, West Palm Beach, Palm Beach)
- S.R. 5/S Federal Highway RRR Project (Lake Worth Beach) — $830,000, expected to begin this month. All lanes open.
- Okeechobee Boulevard at Military Trail and Forest Hill Boulevard at Haverhill Road Lighting Projects (West Palm Beach) — $2.3 million. Okeechobee Boulevard from east of Military Trail to I-95 may lose one lane each direction, 7 p.m.–7 a.m., Sunday, Nov. 15 through Friday morning, Nov. 20. The Okeechobee/Military Trail and Forest Hill/Haverhill intersections may each lose two lanes, 9 p.m.–7 a.m., same nights.
- U.S. 1 RRR Project (West Palm Beach) — $3.9 million, Belvedere Road to Okeechobee Boulevard. One lane each direction may close intermittently, 9 a.m.–3 p.m., Nov. 16–20. The northbound outside lane from Barcelona Road to Acacia Road stays closed through fall 2026.
- S.R. A1A/South County Road, Emerald Beach Way to Royal Palm Way (Town of Palm Beach) — $8.2 million. Final paving runs 8 p.m.–6 a.m., Sunday through Thursday nights, through Friday, Nov. 20, mostly from just south of Gulfstream Road to Royal Palm Way. Expect brief full intersection closures with detours as paving moves through. Daily (8 a.m.–6 p.m.) and nightly (8 p.m.–6 a.m.) flagging-operation lane closures continue, along with sidewalk replacement from Brazilian Avenue to Royal Palm Way and at Hammon Avenue/Golfview Road through November, and southbound closures at Peruvian and Chilean avenues with posted detours via Hibiscus Avenue, Brazilian Avenue and South Ocean Boulevard.
Northern Palm Beach County (Riviera Beach, Lake Park, North Palm Beach, Palm Beach Gardens, Juno Beach, Jupiter, Tequesta)
- U.S. 1 Roadway Improvements (Riviera Beach/Lake Park/North Palm Beach) — $13.4 million, 59th Street to Northlake Boulevard. One lane closes 8 a.m.–4:30 p.m., Nov. 16–21, and 9 p.m.–7 a.m., Nov. 15–20. The northbound sidewalk from Access Road to W 11th Street and the right turn to E 11th Street are closed through December; cruise traffic should use W 13th Street. The center left-turn lane between Silver Beach Road and E. Kalmia Drive is permanently closed.
- S.R. 710/Beeline Highway Reconstruction (Palm Beach Gardens/Riviera Beach/West Palm Beach) — $148.2 million, through late 2029. Daytime lane closures blanket Beeline from Military Trail to Blue Heron Boulevard and at Northlake Boulevard, Jog Road and Haverhill Road, mostly 7 a.m.–6 p.m. weekdays. The Beeline/Jog Road intersection gets nightly closures and U-turn detours, 8 p.m.–6 a.m., through Thursday, Nov. 19. The northwest Beeline ramp to eastbound Northlake stays closed until winter; the southeast left turn to eastbound Blue Heron is closed around the clock through spring 2027 (detour via Military Trail). The Turnpike loses one lane each direction at the Beeline overpass overnight through November.
- ADVANCE NOTICE — Beeline Highway full closure: Beeline Highway from Haverhill Road to North Jog Road will close nightly, 9 p.m.–6 a.m., Sunday, Nov. 30 through Friday, Dec. 5, for Turnpike bridge beam installation. The southbound Turnpike entrance ramp at North Jog Road (Exit 107) closes the same nights. Detours will be posted.
- U.S. 1 Earman River Bridge Replacement (North Palm Beach) — $13.7 million. Southbound traffic is on the new southbound bridge, northbound shifts to the inside lanes, and single lanes close intermittently 9:30 a.m.–5 p.m. daily between Anchorage Drive and Northlake Boulevard. The Earman River channel is closed to boats through spring 2027.
- S.R. 811/Alt. A1A Loxahatchee Bridge Rehabilitation (Jupiter) — $830,000. All lanes open, no marine impacts.
Western Palm Beach County (Wellington, Royal Palm Beach, South Bay, Belle Glade, Pahokee, Canal Point)
- S.R. 7/U.S. 441 RRR at Lake Worth Road — $3.4 million. The shopping plaza entrance and exit on northbound 441 south of Lake Worth Road is closed through Friday, Nov. 20; use the Lake Worth Road entrance.
- Southern Boulevard and S.R. 7/U.S. 441 Ramp Improvements — $8.3 million. One lane each direction on 441 closes intermittently 7 a.m.–5 p.m., Nov. 16–20. The northbound right-turn lane to the eastbound Southern Boulevard on-ramp is closed continuously. The eastbound Southern off-ramp U-turn lane stays closed until fall (detour via Fairgrounds Road U-turn), and the northeast and southeast sidewalks are closed through fall.
- U.S. 27 EAA Reservoir Canal Bridges — $20.9 million. Intermittent single-lane closures 7 a.m.–5 p.m., Nov. 16–20; traffic is shifted east until Dec. 31; the speed limit is cut from 65 to 55 mph.
- S.R. 700/Conners Highway Embankment Repairs — finally done. FDOT gave the $1.3 million project final acceptance on Friday, Nov. 13. One down, 214 to go.
Florida’s Turnpike & Other Notable Closures
- Turnpike Widening, Southern Boulevard to Okeechobee Boulevard — Single lane closures on the Turnpike between Jog Road and north of Okeechobee, 8 p.m.–6 a.m., Nov. 15–19. Full ramp closures: northbound between Jog Road (Exit 98) and Okeechobee (Exit 99), 8 p.m.–6 a.m., Monday, Nov. 16 through Wednesday, Nov. 18 (detour off at Jog Road, north to Okeechobee, east to the Turnpike); southbound between Exit 99 and Exit 98, 8 p.m. Tuesday, Nov. 17 to 6 a.m. Wednesday, Nov. 18 (detour west on Okeechobee to Jog Road). Okeechobee Boulevard loses single lanes between Vista Parkway and West Drive, 8:30 p.m.–6:30 a.m., Nov. 15–19. The northbound N Jog Road left turn to the southbound Turnpike stays closed through late 2027 (detour via Belvedere Road and Pike Road).
- Ocean Ridge — S.R. A1A/Jimmy Buffett Memorial Highway has around-the-clock lane closures through late 2026 for water main work, with a temporary traffic signal alternating traffic. On Tuesday, Nov. 17, the signal is expected to move to just north of Ocean Avenue, by Coconut Lane, to just north of Town Hall.
- Lake Worth Beach — Lake Worth Road from Congress Avenue to Holiday Drive loses one lane each direction, 9 p.m.–4 a.m., Nov. 15–19, for pavement markings.
- Palm Beach — Royal Palm Way at the Royal Park drawbridge will lose one lane at a time, 9 a.m.–3:30 p.m., Monday, Nov. 30 through Thursday, Dec. 10, for pedestrian gate relocation.
- Riviera Beach — Blue Heron Boulevard from Military Trail to U.S. 1/Broadway loses one lane each direction, 9 p.m.–4 a.m., Nov. 15–19, for pavement markings.
County Road & Bridge Closures, City by City
Beyond the state highway work above, Palm Beach County’s Traffic Division lists 193 active or newly changed road and bridge projects for Nov. 16 through Nov. 22. A handful are full closures, not just lane drops: C.R. 827A south of S. Main Street in Belle Glade shuts down Monday, Nov. 16; Hatton Highway from U.S. 441 to Airport Road closes nightly (detour via George Wedgeworth Way); westbound Donald Ross Road at U.S. 1 in Juno Beach closes at night; Holman Drive in Palm Beach Gardens is closed to non-local traffic; and the Pipers Glen Boulevard/El Clair Ranch Road intersection in District 5 is closed, with detours via Jog Road, Military Trail, Woolbright Road and Flavor Pict Road. Everything else, sorted by municipality:
Atlantis
- S. Military Trail approximately 75 feet north of Wenhart Road (District 2) — FPL pothole work. Periodic nighttime north and south bound lane closures.
- S. Military Trail from N. Country Club to Dow Lane (Districts 2 and 3) — FPL underground utility work. Periodic north and south bound lane closures.
- S. Military Trail from Tall Pines Drive to Meadow Green Trail (District 2) — FPL underground utility work. Periodic northbound right lane closure. Periodic eastbound left turn lane closure on Lantana Road.
Belle Glade
- C.R. 827A approximately 300 feet to 1,000 feet south of S. Main Street (S.R. 80) (District 6) — Underground utility work. C.R. 827A will be closed south of S. Main Street on Monday, November 16, 2026. Traffic will be detoured via C.R. 827, U.S. 27 (S.R. 25), Palm Beach Road/S. Main Street (S.R. 80). Periodic north and south bound lane closures with flaggers controlling traffic is possible when the road is open to traffic.
- Torry Island Swing Bridge (W. Canal Street N.) at Lake Okeechobee (District 6) — Bridge maintenance and repair. Periodic lane closures with flaggers controlling traffic. Marine vessels requiring +11’ height clearance are restricted for the duration of the project and need to detour north of Torry Island. Boaters should coordinate with U.S. Coast Guard for current information. Expected completion December 2026.
Boca Raton
- Congress Ave. from Boca Club Blvd. to Yamato Rd. (District 4) — Underground utility work. Periodic southbound lane closures on Congress Ave.
- Clint Moore Road approximately 300 feet east of E. Rogers Circle (District 4) — FPL pole removal. Periodic eastbound right lane closure.
- Military Trl. and Clint Moore Rd. (District 4) — Sidewalk installation. Periodic north and south bound lane closures.
- Linton Blvd. from Homewood Blvd. to Orchard Ln. (District 4) — Underground utility work. Periodic westbound lane closures.
- S. Military Trail approximately 150 feet east of N.W. 4th Street (District 4) — FPL underground utility work. Periodic daytime and nighttime north and south bound right lane closures.
- N. Dixie Highway approximately 220 feet south of N.E. 14th Avenue (District 4) — Underground utility work. Periodic northbound right lane closure.
- N. Military Trail at N.W. 19th Street (District 4) — Driveway connection. Periodic northbound right lane closure.
- N. Dixie Highway approximately 325 feet north of Glades Road (S.R 808) to approximately 220 feet south of N.E. 15th Street (District 4) — Underground utility work. Periodic northbound right lane closure.
- N. Military Trail from 40th Street to Hillsboro Canal (District 4) — Underground utility work. Periodic daytime and nighttime lane closures.
- S. Military Trail at N.W. 19th Street (District 4) — Left turn lane extension. North and south bound lane closures.
- Clint Moore Road from S. Military Trail to east of Park of Commerce Boulevard (District 4) — FPL underground utility work. Periodic east and west bound right lane closures.
- N. Military Trail at N.W. 19th Street (District 4) — Driveway connection. Periodic northbound right lane closure. Periodic southbound left turn lane closure.
Boynton Beach
- Seacrest Boulevard from Boynton Beach Boulevard (S.R. 804) to Hypoluxo Road (District 7) — Underground utility work. Periodic southbound right lane closure. Also in Lantana.
- Barwick Road from Caloosa Pines Road to Coconut Lane (District 4) — Pole removal. Periodic northbound lane closure with flaggers controlling traffic.
- N. Congress Avenue at Miner Road (District 2) — Overhead utility work. Periodic southbound right lane closure.
- S. Congress Avenue from Golf Road/S.E 23rd Avenue to approximately 500 feet south of Ocean Drive (District 4) — Underground utility work. Periodic southbound right lane closure.
- N. Seacrest Boulevard at S. Atlantic Drive (District 7) — FPL pothole work. Periodic north and south bound lane closures.
- Old Boynton Road from approximately 500 feet north of Boynton Beach Boulevard (S.R. 804) to approximately 200 feet south of Glen Arbor Trail (District 7) — Underground utility work. Periodic northbound lane closures with flaggers controlling traffic.
- N. Seacrest Boulevard from S. Atlantic Drive to Arthur Court (District 7) — Underground utility work. Periodic north and south bound right lane closures.
- High Ridge Road from Miner Road to Newport Place (District 2) — Underground utility work. Periodic northbound lane closure with flaggers controlling traffic.
- N. Seacrest Boulevard at N.W. 4th Avenue (District 7) — FPL riser installation. Periodic southbound right lane closure.
- N. Seacrest Boulevard from N.W./N.E. 19th Avenue to Gateway Boulevard (District 7) — Underground utility work. Periodic north and south bound right lane closure.
- Congress Avenue approximately 960 feet south of Ocean Drive (District 4) — FPL pole installation. Periodic southbound right lane closures.
- N. Seacrest Boulevard from Gateway Boulevard to Miner Road (District 7) — FPL underground utility work. Periodic north and south bound right lane closures.
- N. Seacrest Boulevard from N.W. 17th Avenue to N.E. 19th Avenue (District 7) — FPL pole installation. Periodic northbound right lane closure.
- Old Boynton Road at W. Boynton Beach Boulevard (District 7) — Underground utility work. Periodic northbound traffic shift with a police officer controlling traffic.
- S. Congress Avenue approximately 123 feet north of Golf Road (District 4) — FPL underground utility work. Periodic north and south bound right lane closures.
- N. Seacrest Boulevard approximately 19 feet south of N.E. 14th Avenue (District 7) — FPL underground utility work. Periodic north and south bound right lane closure.
- S. Seacrest Boulevard from S.E. 27th Avenue to S.W./S.E. 23rd Avenue (Districts 4 and 7) — FPL pole replacement and underground utility work. Periodic north and south bound right lane closures.
Delray Beach
- Linton Blvd. from Augusta Cir. to Sims Rd. (District 4) — FPL overhead work. Periodic westbound lane closures.
- S. Military Trail approximately 700 feet south of Monterey Lane/Delaire Country Club Boulevard (District 4) — Underground utility work. Periodic northbound right lane closure.
- E. Linton Boulevard at Bascule Bridge (east of Federal Highway) (Districts 4 and 7) — Bridge inspection and maintenance. Periodic east and west bound lane closures.
- S. Congress Ave. from SW 29th St. to Old Germantown Rd. (District 4) — Bridge maintenance. Northbound right-lane closure.
- Linton Boulevard at U.S. 1 (District 7) — Underground utility work. Periodic westbound right lane closures.
- S. Military Trail at Sherwood Boulevard (District 4) — Underground utility work. Periodic northbound right lane closure.
- Lake Ida Road from Davis Road to Congress Avenue (Districts 4 and 7) — Underground utility work. Periodic eastbound right lane closure on Lake Ida Road and southbound right lane closure on N. Congress Avenue.
- Lake Ida Road from Hagen Ranch Road to Congress Avenue (Districts 4, 5 and 7) — Pavement markings/striping. Periodic lane closures.
- W. Linton Boulevard at Catherine Drive (Districts 4 and 7) — Underground utility work. Periodic east and west bound right lane closure.
Greenacres
- Summit Boulevard east of Florida Mango Road (District 3) — Underground utility work. Periodic east and west bound lane closures.
- S. Jog Road at Lake Worth Road (District 3) — FPL underground utility work. Periodic north and southbound right lane closure.
- Sherwood Forest Boulevard from Lake Worth Road to Forest Hill Boulevard (District 3) — Pavement markings. Periodic lane closures.
- 10th Avenue N. from approximately 400 feet west of John I. Leonard High School entrance to approximately 700 feet west of S. Military Trail (District 3) — Underground utility work and pole installation. Periodic east and west bound right lane closures.
- S. Haverhill Road approximately 1,100 feet north of Nautica Isles Boulevard (District 3) — FPL pole installation. Periodic northbound right lane closures.
- S. Military Trail approximately 540 feet south of Canal 14th Road (District 3) — FPL pole installation. Periodic southbound right lane closures.
- S. Haverhill Road from First Street to Bowman Street (District 3) — Underground utility work. Periodic northbound right lane closure.
Juno Beach
- Donald Ross Rd. and US Hwy. 1 (District 1) — Pole removals. Nighttime closure of westbound Donald Ross Rd at US Hwy. 1. Traffic will be detoured south to PGA Blvd. or north to E Indiantown Rd.
- Donald Ross Road at Intracoastal Waterway (District 1) — Bridge maintenance. Periodic lane closures. Also in Palm Beach Gardens.
Jupiter
- S. A1A approximately 150 feet south of Ocean Way (District 1) — Building maintenance access (temporary crane setup). Periodic lane closures with flaggers controlling traffic. The southbound lane and northbound left turn lane will be closed during the daytime with flaggers controlling traffic.
- Limestone Creek Rd. from 4th St. to dead end (District 1) — FPL overhead work. Periodic lane closures with flaggers controlling traffic.
- Central Boulevard from W. Indiantown Road to Longshore Drive (District 1) — FPL riser transfer. Periodic nighttime northbound traffic shift with police officers controlling traffic.
- Frederick Small Road at Military Trail (District 1) — Underground utility work. Periodic westbound right lane closure.
- N. A1A from approximately 200 feet north of Indiantown Road to Jupiter Beach Road (District 1) — Underground utility work. Southbound traffic shift south of Jupiter Beach Road and a partial southbound right turn lane closure north of Indiantown Road.
- Central Boulevard from north of Indiantown Road to Roebuck Road (District 1) — Pavement markings. Periodic lane closures with flaggers controlling traffic.
- Center Street east of Loxahatchee Drive to east of Dolphin Drive (District 1) — Milling and resurfacing. Periodic westbound traffic shift.
Lake Clarke Shores
- S. Florida Mango Road from Garden Drive to Palm Road (District 3) — FPL pole installation and overhead utility work. Periodic north and south bound lane closures with flaggers controlling traffic.
Lake Worth Beach
- 10th Ave N. from Boutwell Rd. to Florida Mango Rd. (District 3) — Underground utility work. Periodic westbound lane closure. Also in Palm Springs.
- 6th Avenue S. approximately 180 feet east of Barber Avenue (District 2) — Underground utility work. Periodic eastbound right lane closure.
Lantana
- Ocean Ave. from N. Dixie Hwy. to ICW Bridge (Districts 4 and 7) — Resurfacing. Nighttime lane closures with police officer controlling traffic.
- Hypoluxo Road from S. 13th Street to S. Broadway (District 7) — FPL underground utility work. Periodic westbound right lane closure.
- W. Lantana Road approximately 119 feet north of N. 3rd Street (District 7) — Underground utility work. Periodic westbound right lane closure.
Mangonia Park
- N. Australian Avenue between N.W. 1st Street to 53rd Street (District 7) — Underground utility work. Periodic southbound right lane closure.
Palm Beach Gardens
- N. Military Trail approximately 200 feet north of Edgemere Lane to Hood Road (District 1) — Underground utility work. Periodic northbound right lane closure.
- N. Military Trail at William T. Dwyer High School (District 1) — Underground utility work. Periodic northbound right lane closure.
- Northlake Blvd. at Landstar Dr./Coconut Crossing Shopping Center (Districts 1 and 6) — Underground utility work. Periodic east and west bound lane closures.
- Northlake Boulevard from Constellation Boulevard to Mount Holly Drive (Districts 1 and 7) — FPL pothole work. Periodic westbound right lane closure.
- Roan Lane approximately 150 feet north of Northlake Boulevard to approximately 80 feet south of Van Cott Street (District 1) — Underground utility work. Periodic northbound lane closures with flaggers controlling traffic.
- Northlake Boulevard approximately 2,000 feet west of Coconut Boulevard to approximately 300 feet east of Coconut Boulevard (District 6) — Driveway installation and median modifications. Periodic east and west bound right or left lane closures.
- Coconut Boulevard approximately 250 feet north of Hamlin Boulevard to Northlake Boulevard (District 6) — Driveway installation and south right turn lane installation. Periodic southbound right lane closure. Periodic westbound left turn lane closure on Northlake Boulevard.
- Northlake Boulevard from Sunrise Drive to east of MacArthur Boulevard (District 1) — Underground utility work. Periodic westbound right lane closure. Periodic northbound left turn lane closures on N. Congress Avenue and Plaza. Periodic southbound right turn lane closure on MacArthur Boulevard.
- Northlake Boulevard east of Bay Hill Drive to west of 112th Terrace N. (District 1) — Drainage installation. Eastbound right lane closure.
- Northlake Boulevard east of Bay Hill Drive to west of 112th Terrace N. (District 1) — Installation of a westbound left-turn lane and raised median. Periodic east and west bound left lane closures.
- Prosperity Farms Road from south of Canal Road to Idle Road (District 1) — FPL overhead maintenance. Periodic northbound right lane closure. Periodic eastbound left turn lane closure on PGA Boulevard.
- N. Military Trail at Kyoto Gardens Drive (District 1) — East side road widening. Northbound right lane and right turn lane closures.
- Holman Dr. from US Hwy 1 to Ellison Wilson Rd. (District 1) — Water and force main installation. Holman Dr. closed to non-local traffic.
- Northlake Boulevard east and west of Bee Line Highway (SR 710) (Districts 1 and 2) — Road widening. Periodic east and west bound lane closures from 10:30 a.m. to 6 p.m. Monday through Saturday. Northlake Boulevard east and west bound lanes have been shifted and U-turns in both directions are not available. Bee Line Highway (SR 710) northwest bound access to eastbound Northlake Boulevard has been shifted. During this phase, Bee Line Highway (SR 710) northwest bound motorists can turn right at the intersection to access eastbound Northlake Boulevard.
Riviera Beach
- President Barack Obama Highway from 500 feet south of W. 1st Street to W. 13th Street (District 7) — Underground utility work. Periodic east and west bound lane closures with flaggers controlling traffic. Also in West Palm Beach.
- Australian Avenue approximately 1,800 feet south of Blue Heron Boulevard (District 7) — Underground utility work. Periodic north and south bound right lane closures.
- Australian Avenue approximately 291 feet north of W. 13th Street (District 7) — FPL pole installation. Periodic nighttime southbound traffic shift with police officers controlling traffic.
- N. Australian Avenue approximately 25 feet south of Fairfield Drive (District 7) — Overhead utility work. Periodic northbound right lane closure.
- N. Haverhill Road approximately 365 feet south of Bee Line Highway (District 7) — FPL pole replacement. Periodic north and south bound traffic shift with a police officer controlling traffic.
- President Barack Obama Highway from W. 11th Street to W. 4th Street (District 7) — Gas main installation. Periodic southbound right lane closure.
Royal Palm Beach
- Crestwood Boulevard from Crestwood Circle to Okeechobee Boulevard (District 6) — Underground utility work. Periodic north and south bound lane closures. Periodic eastbound right turn lane and westbound left turn lane closure on Okeechobee Boulevard.
- Okeechobee Boulevard approximately 300 feet east of Wildcat Way to SR 7 (US 441) (District 6) — FPL overhead maintenance. Periodic east and west bound right lane closure.
Tequesta
- Old Dixie Hwy. from Alt. A1A to County Line Rd. (District 1) — Pavement markings. Periodic lane closure. Day and night operations.
West Palm Beach
- Jog Road at Roebuck Road (District 3) — Emergency road repair. Northbound Jog Road and eastbound Roebuck Road right lane closures.
- N. Congress Avenue from Palm Beach Lakes Boulevard to approximately 1,000 feet south of Northlake Boulevard (District 7) — Underground utility work. Periodic southbound right lane closures. Also in Riviera Beach and Lake Park.
- Congress Ave. approximately 200 ft south of Executive Center Dr. (District 7) — Road improvements. Periodic northbound right lane closure.
- Palm Beach Lakes Boulevard from Sapodilla Avenue E. to Madeira Court (District 7) — Pavement markings. Periodic day and nighttime lane closures.
- 45th Street from Park Avenue to N. Haverhill Road (District 7) — Overhead utility work. Periodic eastbound right lane closure and eastbound right turn lane closure at N. Haverhill Road.
- N. Haverhill Road approximately 100 feet south of 45th Street (District 7) — Overhead utility work. Periodic southbound right lane closure and westbound right turn lane closure at 45th Street.
- N. Australian Avenue approximately 52 feet south of 3rd Street (District 7) — Underground utility work. Periodic southbound right lane closure.
- N. Australian Avenue between 42nd Street and 43rd Street (District 7) — Watermain installation. Periodic north and south bound lane closures.
- N. Congress Avenue approximately 3,700 feet north of Presidential Way (District 7) — Lift station replacement. Southbound right lane closure.
- 45th Street approximately 55 feet west of East Avenue to approximately 530 feet east of East Avenue (District 7) — FPL pole replacements. Periodic westbound right lane closures.
- N. Australian Avenue from 25th Street to approximately 200 feet north of 25th Street (District 7) — Right turn lane installation. Driveway removals and installation. Periodic northbound right lane closure. Periodic westbound right lane closure.
- S. Australian Avenue from I-95 to Okeechobee Boulevard (District 2) — Drainage installation. Periodic lane closures.
Unincorporated Areas & County Roads (by District)
District 1:
- Limestone Creek Rd. from Church St. to Rockwood Rd. — Underground utility work. Nighttime periodic lane closures with flaggers controlling traffic.
- 164th Court N. from 125th Ave. N to Haynie Ln. — Underground utility work. Periodic east and west bound lane closures with flaggers controlling traffic.
- Randolph Siding Rd. from 123rd Terr. N. to Haynie Ln. — Underground utility work. Periodic westbound lane closures with flaggers controlling traffic.
- Alexander Run from approximately 300 ft N. to approx. 500 ft S. of 164th Ct. — Underground utility work. Periodic north and south bound right lane closures with flaggers controlling traffic.
- Donald Ross Road at 64th Drive North — Driveway connection. Periodic west and east bound lane closures.
- W. Indiantown Road approximately 44 feet west of Trailwood Circle — FPL underground utility work. Periodic westbound right lane closure.
District 2:
- S. Military Trl. approximately 0.75 miles (3,960 feet) south of Gateway Blvd. — Road improvements and underground utility work. Periodic northbound right lane closure.
- Le Chalet Blvd. and Jog Rd. — Underground utility work. Periodic north- and eastbound right lane closures.
- Summit Blvd. from approx. 1,500 feet west of Harper’s Ferry Blvd. to Fergusson Ln. — Underground utility work. Periodic westbound lane closures with flaggers controlling traffic.
- Elmhurst Road from approximately 1,200 feet east of N. Haverhill Road to approximately 775 feet west of N. Military Trail — Underground utility work. Periodic east and west bound lane closures with flaggers controlling traffic.
- Jog Road from approximately 700 feet north of Le Chalet Boulevard to approximately 200 feet south of Azura Lake Drive — Underground utility work. Periodic north and south bound right lane closures.
- S. Congress Avenue approximately 346 feet south of W. Atlantic Avenue — FPL underground utility work. Periodic north and south bound lane closures.
- S. Military Trail approximately 750 feet north of Old Boynton Road — Driveway connection. Northbound right lane closure. Southbound U-turn lane closure.
- S. Military Trail approximately 174 feet south of Mirror Lakes Boulevard — FPL underground utility work. Periodic southbound right lane closure.
- S. Congress Avenue from Lantana Road to Hypoluxo Road — FPL underground utility work. Periodic north and south bound right lane closures.
- Hypoluxo Road from High Ridge Road to approximately 1,000 feet west of Interstate 95 — Underground utility work. Periodic eastbound right lane closure.
- N. Haverhill Road approximately 880 feet north of Okeechobee Boulevard — Underground utility work. Periodic southbound right lane closure.
- Jog Road at Gun Club Road — Underground utility work. Periodic northbound lane closure. Periodic traffic shifts with police officers and flaggers controlling traffic on Gun Club Road.
- N. Haverhill Road from approximately 465 feet north of Stacy Street — FPL pole installation. Periodic northbound right lane closure.
- Military Trail approximately 375 feet south of Lantana Road — FPL underground utility work. Periodic north and south bound right lane closures.
- Jog Road approximately 262 feet south of Pioneer Road — Underground utility work. Periodic southbound right lane closure.
- N. Haverhill Road at Southern Boulevard — FPL underground utility work. Periodic northbound right lane closure.
- Hypoluxo Road at Florida Drive — FPL underground utility work. Periodic westbound right lane closure.
- S. Congress Avenue approximately 262 feet south of Lantana Road — FPL underground utility work. Periodic north and south bound right lane closures.
- S. Cleary Road from Dillman Road to Pioneer Road — FPL pole replacements. Periodic southbound lane closure with flaggers controlling traffic (moving operation).
- Old Boynton Road from S. Military Trail to approximately 450 feet west of Lawrence Road — Underground utility work. Periodic westbound right lane closure.
- Australian Avenue from W. 1st Street to W. 4th Street — Gas main installation. Periodic north and south bound right lane closures.
- Wallis Road from Hach Lane to Marguerita Drive — FPL underground utility work. Periodic east and west bound lane closures with flaggers controlling traffic.
- N. Cleary Road approximately 80 feet north of Westport Place to approximately 225 feet north of Westport Place — FPL underground utility work. Periodic north and south bound lane closures with flaggers controlling traffic.
District 3:
- Haverhill Rd. from Navarre Rd. to Lake Worth Rd. — FPL underground work. Periodic northbound right lane closure.
- 10th Ave N. from N. Detroit St. to Florida Mango Rd. — Underground utility work & pole installation. Periodic east and west bound lane closures.
- Canal Road from Sleepy Hollow Road to S. Military Trail (S.R. 809) — Underground utility work. Periodic eastbound lane closure with flaggers controlling traffic.
- Sunset Lane from beginning to S. Military Trail (S.R. 809) — Underground utility work. Periodic east and west bound lane closures with flaggers controlling traffic.
- Melaleuca Ln. from Gulfstream Rd. to Military Trl. — Underground utility work. Periodic westbound lane closure.
- Military Trl. from Barclay Crescent to Coventry Pointe Way — Underground utility work. Periodic northbound lane closure.
- S. Haverhill Road from Cresthaven Boulevard to Purdy Lane — FPL overhead utility work. Periodic northbound right lane closure.
- Kirk Road approximately 175 feet north of Gun Club Road — Driveway connection. Periodic northbound right lane closure.
- Melaleuca Lane at Mee Court — Underground utility work. Periodic right lane closure.
- Gun Club Road at Pheasant Run Boulevard — FPL riser transfer. Periodic eastbound traffic shift.
- Melaleuca Lane approximately 320 feet east of S. Military Trail — FPL underground utility work. Periodic eastbound right lane closure.
- S. Military Trail approximately 1,185 feet south of Melaleuca Lane — FPL underground utility work. Periodic northbound right lane closure.
- S. Haverhill Road at Purdy Lane — Underground utility work. Periodic southbound right lane closure.
- Summit Boulevard approximately 591 feet west of S. Military Trail — Roadway improvements. Periodic eastbound right lane closure.
- 10th Avenue North approximately 360 feet west of Boutwell Road — Driveway connection. Periodic westbound lane closures.
- Summit Boulevard approximately 500 feet west of S. Military Trail — Water main connection. Periodic eastbound lane closures.
- S. Military Trail approximately 605 feet south of Lake Worth Road — FPL underground utility work. Periodic north and south bound lane closures.
- S. Military Trail from approximately 200 feet south of Maine Street to approximately 400 feet north of Fuller Street — Underground utility work. Periodic northbound right lane closure on S. Military Trail. Periodic eastbound left turn lane closure on Melaleuca Lane.
- S. Haverhill Road at Summit Pines Boulevard — FPL pole replacements. Periodic southbound lane closure with traffic shift.
- S. Haverhill Road approximately 500 feet south of Summit Pines Boulevard — FPL pole replacements. Periodic southbound lane closure with traffic shift and a police officer controlling traffic.
- S. Haverhill Road from Royal Court S. to Royal Court N. — FPL pole replacements. Periodic northbound lane closure with traffic shift and a police officer controlling traffic.
- Summit Boulevard approximately 590 feet west of S. Military Trail — Right turn lane extension. Periodic eastbound right lane closure.
- S. Haverhill Road approximately 30 feet north of Carver Street — Underground utility work. Periodic northbound right lane closure.
- 10th Avenue approximately 28 feet west of Greene Avenue — Underground utility work. Periodic eastbound right lane closure.
- Charleston Street approximately 1,360 feet south of Lake Worth Road (S.R. 802) — Underground utility work. Periodic southbound lane closure with flaggers controlling traffic.
- S. Haverhill Road approximately 30 feet south of 2nd Street — Underground utility work. Periodic northbound right lane closure.
- Cresthaven Boulevard approximately 50 feet east of S. Haverhill Road — Underground utility work. Periodic westbound right turn lane closure.
District 4:
- Powerline Road approximately 104 feet north of W. Palmetto Park Road — FPL pole installation. Periodic nighttime southbound double lane closure.
District 5:
- Glades Road approximately 400 feet east of Sandpiper Shores Elementary School to approximately 200 feet west of Diego Drive N/Diego Drive W. — Underground utility work. Periodic eastbound right lane closure and westbound right turn lane closures.
- Clint Moore Road from S.R. 7 to Lyons Road — FPL underground utility work. Periodic eastbound right lane closure.
- Flavor Pict Road at Hagen Ranch Road — Underground utility work. Periodic westbound traffic shift with police officer controlling traffic.
- Clint Moore Road approximately 1,150 feet west of Woodfield Circle — Pole installation. Periodic east and west bound right lane closures.
- El Clair Ranch Road from Atlantic Avenue to Boynton Beach Boulevard — Pavement marking/striping. Periodic lane closures.
- Flavor Pict Road approximately 600 feet east of Green Cay Farm Boulevard — FPL underground utility work. Periodic westbound traffic shift.
- Lyons Road approximately 355 feet north of Kimberly Boulevard — Watermain replacement. Periodic north and south bound left lane closures.
- Hagen Ranch Road approximately 85 feet southwest of Castle Gate Boulevard — FPL pole replacements. Periodic nighttime southbound traffic shift with police officers controlling traffic.
- S. Military Trail approximately 181 feet south of Palm Ridge Boulevard — Underground utility work. Periodic north and south bound right lane closures.
- S.W. 13th Place at Sandalfoot Boulevard — Lift station relocation and underground utility work. Periodic lane closures.
- Pipers Glen Boulevard and El Clair Ranch Road — Intersection improvements. Pipers Glen Boulevard and El Clair Ranch Road is closed. Traffic will be detoured via S. Jog Road, S. Military Trail, Woolbright Road and Flavor Pict Road.
District 6:
- Hatton Hwy. from U.S. Hwy. 441 to Airport Rd. — FPL overhead work. Hatton Hwy. will be closed nightly with traffic detoured to George Wedgeworth Way.
- Royal Palm Beach Blvd. from Orange Blvd. to 54th St. N. — FPL pole installation. Periodic lane closures with flaggers controlling traffic.
- Hypoluxo Road at Lyons Road — Gas main extension. Periodic eastbound lane closures.
- Lyons Road at Gulf Run Way — Driveway connection. Periodic north and south bound lane closures.
- Lyons Road approximately 1,200 feet south of Perth Road — Construction entrance. Periodic north and south bound lane closures with flaggers controlling traffic.
- Lantana Road from Lyons Road to Aquarius Boulevard — FPL cable and riser replacement. Periodic east and west bound lane closures.
- Lyons Road and Gulf Run Way — Driveway connection. Periodic southbound right lane closure.
- Okeechobee Boulevard from Royal Palm Beach Boulevard to Crestwood Boulevard — Underground utility work. Periodic eastbound right lane closures.
- W. Sycamore Drive approximately 130 feet east of Cheetham Hills Boulevard to Seminole Pratt Whitney Road — FPL underground utility work. Periodic eastbound lane closure with flaggers controlling traffic. Periodic eastbound right turn lane closure.
- Seminole Pratt Whitney Road from Southern Boulevard (SR 80) to Sycamore Drive — FPL underground utility work. Periodic south and north bound right lane closures.
- Dillman Road from Lyons Road to east of Marginal Road — FPL pole replacements. Periodic day and nighttime lane closures with flaggers controlling traffic.
- Lyons Road approximately 500 feet north of Forest Hill Boulevard to approximately 300 feet north of Estate Drive — FPL pole replacements. Periodic southbound traffic shifts and flagging operation.
- Belvedere Road approximately 3,700 feet east of SR 7/US 441 — Force main connection, driveway and sidewalk replacement. Restoration of median. Periodic nighttime eastbound double lane closures. Periodic daytime eastbound left lane closure.
- Lyons Road from approximately 140 feet south of Lantana Road to approximately 230 feet south of Twig Road — FPL pole and streetlight installation. Periodic north and south bound right lane closures.
- Northlake Boulevard from Seminole Pratt Whitney Road to Hall Boulevard — Road widening, construction project. Periodic east and west bound lane closures with flaggers controlling traffic.
- Seminole Pratt Whitney Road from 71st Place N. to north of 86th Road — Culvert installation and median installation. Northbound lane closure with traffic shift. Southbound traffic shift and left turn lane closure at 71st Place N.
District 7:
- Overlook Road from Miner Road to Seagrape Road — Underground utility work. Periodic lane closures with flaggers controlling traffic.
- Hypoluxo Road at Sea Pines Way — FPL underground utility work. Periodic westbound right lane closure.
- N. Florida Mango Road approximately 196 feet east of Latham Road — FPL pole installation. Periodic northbound lane closures with flaggers controlling traffic.
- Westgate Avenue from Seminole Boulevard to west of Osceola Drive — Underground utility work. Periodic east and west bound traffic shifts with police officers controlling traffic.
- Westgate Avenue approximately 40 feet west of Congress Avenue — Underground utility work. Periodic westbound traffic shift.
Districts 2 and 3:
- N. Military Trl. approximately 200 ft south of Lantana Rd. — FPL pothole work. Periodic northbound and southbound lane closures.
Districts 4 and 5:
- Clint Moore Rd. approx. 0.20 miles east of Claridge Oval W. — Entrance modification. Periodic eastbound lane closures.
Districts 5 and 6:
- Lyons Road from Boynton Beach Boulevard to Hypoluxo Road — Refurbishing existing thermoplastic. Periodic lane closures.